9.8.08

Ahmedabad's Flyovers and RoBs

FLYOVERS
1 Shivranjani Junction : Busy commercial hub with corporates and big shopping complexes Deadline: Project completed, inauguration awaited Present status : Project completed
2 Memnagar Crossroads :BRTS corridor, also a huge traffic bottleneck for vehicles coming from Thaltej crossroads towards Vijay cross roads Deadline: With in six months Present status: Project near its completion date, will be finished in six months
3 AEC Sola Four-lane Flyover:To reduce travelling time for commuters coming or going from Sola-SG road, also a major traffic bottleneck Deadline: Not specified Present status: 31 per cent work ompleted
4 Soni ni Chali Junction Split Flyover:BRTS corridor, national highway Deadline: Not specified Present status: Still in tendering process
5 Thakkerbapanagar Junction Split Flyover : BRTS corridor, national highway Deadline: Not specified Present status: Still in tendering process
RAILWAY OVERBRIDGES
6 Parimal Garden RoB : A hub of doctors’ clinics and hospitals and a major traffic bottleneck Deadline: Not Specified Present status: Direct work permission received from the railway board; work yet to begin
7 Chanakyapuri Junction RoB : Notorious for long traffic snarls and minimum waiting time of 10 minutes Deadline: Not specified Present status: Approach road completed; railways work is in progress
8 Gota RoB : Heavy vehicles passing the road lead to more traffic. It will reduce travelling time for people going to and fro Sarkhej Deadline: Not specified Present status: Under progress
9 Ladla Pir Railway Crossing : Will make travel shorter by 3 km for people coming from Delhi Darwaza towards Shahibaug, Girdharnagar, Civil hospital and cantonment area Deadline: Not specified Present status: Work on the approach road in progress; Railway Board’s approval for work on the track awaited. Approach road work completed, 40 per cent work completed
10 Omkar Crossing RoB : Heavy traffic at Narol-Naroda highway, also a state highway to Panchmahals, Dahod, among other districts. It will become an easy route to reach Airport and Gandhinagar. Civil hospital will be more accessible. Deadline: September 2009 Present status: Approach road work completed over the track
11 Daxini Society Junction RoB : Direct approach from Hatkeshwar, 132 feet Ring Road, travelling distance will be cut down by four km from Isanpur to Hatkeshwar and to reduce traffic blockage. Deadline: Not specified Present Status: Approach road work completed, railways’ work yet to be completed
12 Vatva, GIDC RoB : Direct access to GIDC for vehicles, Vatva residents can directly approach Vadodara Expressway and Sardar Patel Ring road. It will also help in decreasing road accidents on NH 8 Deadline: Not specified Present status: Approach road work in progress, Railway Board’s approval for work on track by AMC awaited